Monthly Archives: August 2012

Update on the Claire T. Carney Library & FAQs about the Library Closure

The following is an update on the Carney Library closure from Deb McLaughlin, COO and Vice Chancellor. It was sent to the campus community on the evening of Tuesday, August 21st.

“Floors 4 and 5 are reopening to the public tomorrow. Floor 3 has also been given a “temporary certification of occupancy” as part of ongoing construction, and we expect that construction Floors 1 and 2 will continue on schedule. We still plan on opening the Library on schedule in time for the Fall Semester.

Today, we brought local media into the Library for a tour of affected and unaffected areas, and we held a staff meeting for all current and future Library occupants.

At today’s meeting, our colleagues asked questions that we believe all members of the campus community – staff, faculty, students and their parents – might ask if they were in the room. Therefore, we are providing a list “frequently asked questions” below, which we will also be posting in public areas.

FAQs

What happened?
During re-roofing operations of a small section of the main library roof, the temporary measures that were installed during the previous day’s operations by the roofing subcontractor were overwhelmed during Wednesday morning’s storm. The above average rainfall (2-inches in under an hour) infiltrated mechanical shafts and affected areas mainly on the 5th and 4th floors. As a result of the breach, water caused minor damage to an isolated amount of ceiling and carpet tiles, pipe insulation, shaft wall and fire alarm and electrical system components. Out of an abundance of caution and to ensure the response to the incident was swift and comprehensive, the building was evacuated. Emergency specialists were immediately contacted and repair work started immediately.

Did this affect health and safety?
There have been no reports of any individual’s health or safety being compromised during or after the incident. Testing has shown that air quality remained healthy at all times. The University, in fact, tested for 23 different potential hazards (rust, mold, moisture, etc.) and the results provided confidence that people could safely return to the building.

What is the University doing to follow up on health and safety issues?
Multiple air quality tests have been completed by two different companies (Cashins for the contractor and Mabbett for the University) and overseen by a third firm, ATC, hired by the state Division of Capital Asset Management (DCAM). University testing has shown that the air quality inside the building is actually better than the air outside the building. The technical reports are available for anybody wishing to read them. We are also asking DCAM to have the contractor carry out additional tests as the construction continues, again out of an abundance of caution.

Should we be concerned about mold growing in the months and years to come as a result of this incident?
There is no reason to believe this incident will have any long-term effect on air quality in the building.

What kind of damage was done, and who is going to pay for it?
DCAM is working on an estimate of damage costs. The University is compiling costs related to employees not being able to work while the library was closed. Due to the contract we signed with DCAM, we do not expect the University will pay any of the costs of the repair work.

Who should we notify if we notice something relative to health and safety?
Please immediately inform you supervisor who should bring the issue to the Office of Environmental Health and Safety at X8176.

How are payroll issues being addressed?

In general, people who could not work as a result of the incident will be paid in full for work time lost. For information related to a specific employee, please contact the Office of Human Resources at X8060.

Will there be any system shutdowns in the future?
No additional system-wide shutdowns are expected, however, as a normal part of the ongoing construction process there may be brief, occasional and partial shutdowns for testing or maintenance.

Why didn’t the University provide more details sooner?
The practice of the University is to provide information as facts become known. In this case, our top priority was evacuating people from the building to assure a safe and timely cleanup, then gathering the facts in order to inform the campus community. Facts were made available to every member of the campus community and the media as they became known.”

Update on the damage assessment, cleanup, repair and reopening efforts after Wednesday’s storm that affected the Claire T. Carney Library.

The Carney Library will re-open to staff tomorrow and to the public on Wednesday, August 22nd.

The following is the official update from Deb McLaughlin, COO and Vice Chancellor for Administration and Finance:

“This is an update on the damage assessment, cleanup, repair and reopening efforts after Wednesday’s storm that affected the Claire T. Carney Library.

As already announced, the Library has reopened to senior staff. We will reopen floor 4 to staff tomorrow, Tuesday, August 21. All staff assigned to floor 4 must report to work tomorrow.

Repair and remediation work on floor 5 is nearly completed and will reopen to staff tomorrow and to the public on Wednesday.

Despite the challenges of the last week, the construction and renovation effort is on schedule, and we expect to have the Library open to all staff, faculty, students and members of the public in time for the start of the Fall Semester.

I want to personally thank each member of staff for your patience during this process.”

Update on the damage assessment, cleanup, repair and reopening efforts after Wednesday’s storm that affected the Claire T. Carney Library

Update on the Claire T. Carney Library

This is an update on the damage assessment, cleanup, repair and reopening efforts after Wednesday’s storm that affected the Claire T. Carney Library.

We have received results from additional air quality tests carried out by an independent firm working for the contractor carrying out renovation work on the Library. This is in addition to results of testing by the independent firm contracted by the University, which is also verifying the findings of the contractor’s firm.

Based on the results of all these tests, we continue to have confidence in our schedule to readmit staff as announced on Friday.

We will partially reopen the Library to senior staff tomorrow, Monday, August 20, and their role will be to assess the state of physical assets in the offices and ensure we are ready to reopen floor 4 to staff on Tuesday, August 21. All other employees assigned to the Library will not report to work on Monday.

Please note that we expect floor 4 to reopen to staff only on Tuesday, August 21, and will confirm whether or not we are ready to do so tomorrow, Monday, August 20. Floor 5 will remain closed to all but essential repair personnel until repairs are completed. Floors 1-3 are subject to ongoing construction, and we will announce their opening to staff at a later date.

Deb McLaughlin
COO and Vice Chancellor for Administration and Finance

Update on the Claire T. Carney Library – August 17th

The following is the most recent update from Deb McLaughlin, COO and Vice Chancellor for Administration and Finance:

“Staff from the University, the state Division of Capital Asset Management (DCAM), which oversees the renovation work, and Consigli, the contractor carrying out the renovation work on the roof, have continued to assess the situation. Outside experts have also been brought in by the University, DCAM and Consigli to independently verify the progress of the work and assist in damage assessment.

We can announce that Mabbett and Associates, the independent firm hired by the University to test 23 different metrics of possible health and safety hazards in the Library due to water leakage, has released the positive results of these tests.

Our greatest concern was about possible mold. Using the outside fresh air as a baseline (with mold spores measured at 4,910 per cubic meter), we identified no area in the Library with a mold spore ratio of more than that in the basement, at 1,490 per cubic meter. Even in the fourth and fifth floors, which were directly affected by water leaks, mold spore levels are much lower than the outside air.

The full report by Mabbett and Associates will be made available for review at the University’s Department of Public Safety beginning on Monday, where Bob Casparius and Amy Kampersol in the Office of Environmental Health and Safety, will be on hand to answer questions.

As a result of these tests, and this weekend’s ongoing assessment and repair work on the fifth floor, we will be partially reopening the Library only to senior staff on Monday, August 20. Their role will be to assess the state of physical assets in the offices and ensure we are ready to fully reopen floors 1-4 to staff on Tuesday, August 21. The senior staff assigned to the assessment task will be contacted by their supervisor or a university administrator and asked to report to work on Monday. All other employees assigned to the Library will not report to work on Monday.

Please note that we expect floors 1-4 to reopen to staff only on Tuesday, August 21, and will confirm whether or not we are ready to do so on Monday, August 20. Floor 5 will remain closed to all but essential repair personnel until repairs are completed.”

We will keep you posted as we learn more.

Update on the Claire T. Carney Library

Deb McLaughlin, COO and Vice Chancellor for Administration and Finance, provided the following update:

“On Wednesday, August 15, UMass Dartmouth was affected by torrential rain
that swept through the SouthCoast. In less than an hour between 9 a.m. and
10 a.m., the campus sustained almost 2 inches of rain, which affected the
Claire T. Carney Library.

As part of an ongoing 3-year renovation project, work was being done on the
roof of the Library. Water entered the Library’s fifth floor and water
leaked into the fourth floor. Thanks to quick action by members of Library
staff, books that could have been affected by the water were removed to safe
areas and the Library was immediately evacuated.

Staff from the University, the state Division of Capital Asset Management,
which oversees the renovation work, and Consigli, the contractor carrying
out the renovation work on the roof, acted to stop any water leaks, assess
damage and begin necessary repairs.

As a result, the decision was made last night by the University to close the
Library until Monday, August 20, in order to allow the cleanup, assessment
and repair process to move as quickly and safely as possible.

Throughout this process, the primary concern of the University and our
partners has, and will continue to be the safety of students, employees and
members of the community who use the Library.

Out of an abundance of caution, access to the Library has been restricted to
individuals who are engaged in the assessment and cleanup. As of today, the
University still expects the Library to reopen on Monday, August 20, pending
the results of the assessment.”

We will continue to keep you posted as we learn more. Again, we are sorry for the inconvenience!

Carney Library closed until Monday, August 20

Due to the effects of water damage caused by this morning’s storm, the Claire T. Carney Library will remain closed until Monday, August 20th. Over the next several days, personnel will continue their assessment of damage and cleanup, and begin repairs to affected areas. The University has decided to keep the Library closed through this weekend to make this effort as efficient, effective and safe as possible.

Access to online library resources and services will continue to be available.

We are very sorry for the inconvenience!